Riders are Feeling the Difference on Geary

Riders are Feeling the Difference on Geary
By

Image of 38 Geary bus and new improved crosswalks on Geary Boulevard

The results are in: the Geary Rapid Project has delivered a faster, more reliable bus trip and a safer street, according to the SFMTA’s recently published evaluation report for the project.  

A faster, more reliable bus ride 

One out of every ten passengers stepping onto a Muni vehicle will ride on Geary Blvd., which makes reducing travel time on the corridor a key piece of improving transit in the city. The transit lanes installed as part of the Geary Rapid Project protect buses from traffic congestion, while smarter traffic signals allow buses to get green lights more often. Similar transit upgrades have been made across the city as part of the Muni Forward program, making your next San Francisco destination closer than ever. 

Transit travel time improved after the quick-build phase of the Geary Rapid Project in late 2018 and early 2019, and again after the full project was completed in 2021 — with savings as great as 18%. Westbound travel times generally improved the most — up to 3.6 minutes during the PM peak — providing a daily 38R Geary Rapid rider 18 hours of savings per year. Although the biggest time savings were seen during commute hours, with 36,000 riders traveling on Geary around the clock each day, even smaller gains outside of peak hours adds up to major travel time savings for all Geary riders combined.  Travel time reliability also improved up to 37%, which means that the time spent waiting for the next bus is more consistent. 

A safer street  

Reducing Muni-involved collisions is critical to protect our passengers and operators. It also keeps Muni service running smoothly; even non-injury collisions cause buses to be taken out of service. Adding dedicated transit lanes on Geary Boulevard has substantially reduced the rate of Muni-involved collisions on the corridor. The collision rate of 38/38R buses decreased by two-thirds and is now about half that of the current citywide Muni bus collision rate. Several years of data will be necessary to fully evaluate the project’s impacts on reducing traffic collisions in general. But one promising indicator is that there was a 70-80% reduction in vehicles traveling over 40 mph (more than 5 mph over the speed limit). A suite of improvements to calm the “expressway” section of the corridor, including a reduction in general-purpose travel lanes to two per direction, new crosswalks, narrower travel lanes and bulb-outs (sidewalk extensions) were implemented to encourage people driving to slow down. 

Graph comparing the share of vehicles traveling faster than 40mph before and after the Geary Rapid Project was implemented. At Laguna Street, speeding rates dropped from about 16% to 3% of vehicles. At Baker Street, speeding rates dropped from about 10% to 3% of vehicles. Before counts were taken in 2016-2017. After counts were taken in 2022.

Comparison graph of 40 mph travel speeds before and after the Geary Rapid Project. 

 

Keeping transit lanes clear 

One of the final portions of the project was painting the transit lanes red. This “red carpet” treatment makes it easier for drivers to know where they’re allowed to drive. When we make transit lanes extra clear with red paint, drivers are less likely to get a citation for unintentionally driving in a transit lane. Previous SFMTA studies showed that the number of private vehicles illegally using transit lanes declines about 50% when the lanes are painted red. Sure enough, the number of vehicles entering the lanes on Geary dropped by 47% from 2019 to 2022, even as traffic congestion returned after COVID restrictions eased (vehicles driving legally in the transit lane to turn right or access curbside parking or driveways were not included). 

The full evaluation report is available on the SFMTA website and covers several additional metrics, including street space allocation, Muni customer experience and parking availability. 

The success of the Geary Rapid Project has informed the final design for the second phase of upgrades, the Geary Boulevard Improvement Project, which proposes to expand these improvements west into the Richmond District.  

A photo is worth a thousand words to show the improvements made on Geary Boulevard. These birds-eye shots provide representative examples of the street design on Geary before (August 2018) and after implementation (February 2022) of the Geary Rapid Project.



Published December 09, 2022 at 04:02AM
https://ift.tt/zF81jds

Comments

Popular posts from this blog

Show HN: Launch VM workloads securely and instantaneously, without VMs https://ift.tt/2QwJ1Kd

Show HN: Launch VM workloads securely and instantaneously, without VMs Hello HN! We've been working on a new hypervisor https://kwarantine.xyz that can run strongly isolated containers. This is still a WIP, but we wanted to give the community an idea about our approach, its benefits, and various use cases it unlocks. Today, VMs are used to host containers, and make up for the lack of strong security as well as kernel isolation in containers. This work adds this missing security piece in containers. We plan on launching a free private beta soon. Meanwhile, we'd deeply appreciate any feedback, and happy to answer any questions here or on our slack channel. Thanks! April 29, 2021 at 07:50AM

Women Pioneers at Muni: Adeline Svendsen and Muni’s First Newsletter

Women Pioneers at Muni: Adeline Svendsen and Muni’s First Newsletter By Jeremy Menzies To close out Women’s History Month, here’s a look back at one woman whose work to bring Muni staff together in the late 1940s created a legacy that lives on to this day. Adeline “Addy” Svendsen was founding editor of Muni’s first internal newsletter, “ Trolley Topics .” Adeline Svendsen sits at her desk in the Geneva Carhouse office building in this 1949 shot. Trolley Topics was a new venture when it started in February 1946. As Svendsen wrote in the first issue it was created, “to bring a little fun, a little news, and a lot of good will to all our fellow employees in the Railway.” Just two years prior in 1944, Muni merged with the Market Street Railway Company, expanding the small municipal operation into the largest transit provider in the city with hundreds of employees, vehicles of every shape and size, and dozens of facilities scattered across town. The newsletter was meant to help unite ...

Show HN: Comment on live websites just like you comment on Google Docs/Figma https://ift.tt/GRhrjX0

Show HN: Comment on live websites just like you comment on Google Docs/Figma I'd love your feedback on this new JS plugin we launched. With this, you can comment on live websites just like you comment on Google Docs or Figma. You can use is to get Copy or UI feedback right on the website you are building. Feedback can be provided in rich formats like audio and video. You can get started by installing a JS tag in the footer of the website. You can then turn the review mode on or off on demand by adding “?review=true” to the URL. Demo video (43s): https://www.youtube.com/watch?v=cdnfBEw8TfI Demo video: https://www.youtube.com/watch?v=h6vxzXJuh8o https://ift.tt/ocLpdEu October 26, 2022 at 02:18AM